The CECs, which provide an all-welded steel enclosure for storage of the multi-purpose canisters (MPC), were manufactured at Holtec Manufacturing Division in Pittsburgh, PA. Each CEC will hold one MPC-37 canister (capacity=37 PWR assemblies) giving the Callaway ISFSI an initial installed capacity of 1776 fuel assemblies. The MPCs were co-produced by HMD and Orrvilon, Inc. (Holtec’s wholly owned subsidiary located in Orrville, Ohio). All 48 CECs are set, verticality checked, and grouting of each is complete. The Holtec Site Services team averaged 7 CECs set/day vs. the goal of 4-6/day. The team finished setting the CECs in 7 days vs. the anticipated 12 days. The photo below shows the CECs with the biological lid placed on each silo. |